Here are some of the highlights of the construction progress taking place in The Cosmopolitan Condominiums:

  • stairways 1 and 2 are installed up to 22
  • door and trim installation are starting on 3
  • 2nd container of Pedini cabinets have been received
  • drywall taping and finishing on 2 and 3
  • prime and first coat of paint on 2 and 3
  • interior unit pre-hung doors on 2
  • installation of pocket door frames through 9 and 10
  • hanging pocket doors on 2
  • tile installation on 2 and 3 wood flooring on 2
  • Benson curtain wall installation is almost complete
  • all concrete decks have been installed up to level 29/roof
  • material/man lift has jumped to 28